- PM Modi visit USAOnly the mirror in my washroom and phone gallery see the crazy me : Sara KhanKarnataka rain fury: Photos of flooded streets, uprooted treesCannes 2022: Deepika Padukone stuns at the French Riviera in Sabyasachi outfitRanbir Kapoor And Alia Bhatt's Wedding Pics - Sealed With A KissOscars 2022: Every Academy Award WinnerShane Warne (1969-2022): Australian cricket legend's life in picturesPhotos: What Russia's invasion of Ukraine looks like on the groundLata Mangeshkar (1929-2022): A pictorial tribute to the 'Nightingale of India'PM Modi unveils 216-feet tall Statue of Equality in Hyderabad (PHOTOS)
Hockey India on Monday announced the 20-member squad for the Men's Junior Asia Cup, a qual
- Harmanpreet Singh named FIH Player of the Year, PR Sreejesh gets best goalkeeper award
- World Boxing medallist Gaurav Bidhuri to flag off 'Delhi Against Drugs' movement on Nov 17
- U23 World Wrestling Championship: Chirag Chikkara wins gold as India end campaign with nine medals
- FIFA president Infantino confirms at least 9 African teams for the 2026 World Cup
- Hockey, cricket, wrestling, badminton, squash axed from 2026 CWG in Glasgow
Supreme Court cancels Amrapali Group's RERA registration, orders NBCC to complete pending projects Last Updated : 23 Jul 2019 01:27:53 PM IST Giving respite to the 42,000 beleagured buyers of Amrapali Group, the Supreme Court on Tuesday cancelled the real estate company's Real Estate Regulation and Development) Act registration and appointed state-run National Buildings Construction Corporation Limited (NBCC) to complete all its pending projects.
A bench, comprising Justice Arun Mishra and Justice U.U. Lalit, also noted that Amrapali Group had committed a major violation of Foreign Exchange Management Act (FEMA) and foreign direct investment (FDI) norms and directed the Enforcement Directorate (ED) to register a money laundering case against the company, its CEO and Managing Director (CMD) Anil Sharma, and directors Shiv Priya and Ajay Kumar.
The court also ordered attachment of properties of the CMD and directors.
The court observed that Amrapali Group's top management diverted homebuyers' money to build their personal assets, instead of completing its housing projects. "The top management of Amrapali Group siphoned off the money to foreign countries," said the court. Noida and Greater Noida authorities were negligent in monitoring the progress of the project, the court said.
Reserving a verdict in the case, the apex court had on May 10 noted that the homebuyers had already paid the company Rs 1,100 crore, which was more than the cost of its projects. The court had asked banks and the authorities concerned, if the projects could be taken over by Noida and Greater Noida authorities for completion.
Pleading that they do not have the requisite resources and expertise to complete the construction of the stalled projects, the Noida and Greater Noida authorities asked the bench to hand them over to a reputed builder. They also requested the court to set up a high-powered committee to supervise the completion of the projects in a time-bound manner.
The court said the lenders' had no right to sell the properties, which largely constitute homes for which buyers have paid, to recover their losses and instead asked them to recover their losses from Amrapali Group's CMD and directors.
Responding to the court's query on the action taken against Amrapali Group, which was a chronic defaulter on lease amounts, the Noida authority said it had jurisdiction over seven projects of the company but had received only Rs 505 crore out of its nearly Rs 2,000 crore outstanding dues.
The Greater Noida authority told the court that it had five projects of Amrapali Group under its jurisdiction, four of which were vacant plots where no construction had taken place. "The company has an outstanding of around Rs 3,400 crore and has paid only Rs 363 crore till now," it added.
The two authorities also expressed their inability to take action like cancellation of lease agreements of the group.
Several pleas have been filed by homebuyers seeking possession of around 42,000 flats booked in projects of Amrapali Group.IANS New Delhi For Latest Updates Please-